top of page

First Fix Carpentry in Putney

Project background and scope

This ongoing residential refurbishment in Putney includes first-fix carpentry throughout the property. The case study follows the floor structures, timber partitions and construction-stage progress before final finishes.

The scope included the replacement and strengthening of existing floor joists, installation of new timber floor structures, acoustic insulation and soundproof flooring systems to improve noise performance between levels. New timber partitions were also constructed to form the revised room layouts and prepare the property for the next stages of the refurbishment.

All carpentry works were completed accurately to suit the architectural layout, building regulations and the requirements of the following mechanical, electrical, plastering and finishing trades.

CASE STUDY | 51 Werter Road, Putney

Work in progress - updated October 2026

The progress gallery follows the refurbishment as the internal spaces take shape. Selected photographs show timber ceiling framing, ground-floor preparation, staircase installation, boarded loft rooms and the installation of underfloor heating and associated services. These are construction-stage photographs, before final decoration and fittings.

Further progress photographs and completed views will be added to this case study as the project continues.

Project type: First Fix Carpentry, Timber Partitions and Floor Joist Replacement

Date: July 2026 – Present

Location: Putney, London

Status: Work in progress - photo update October 2026

Structure

Ground-floor renovation and structural preparation in Putney

Structure - Ground-floor renovation

Timber ceiling joist framing during structural works

Structure - Timber ceiling framing

Exposed timber floor joists spanning a room with stripped brick walls.

Structure – Exposed floor joists and masonry walls

Open floor structure beneath a window during internal refurbishment.

Structure – Stripped room and open floor structure

Room with the floor removed, exposed brickwork and access equipment during construction.

Structure – Floor removed during internal refurbishment

Floor decking partly installed around a temporary workbench beneath exposed ceiling joists.

Structure – Floor decking installation in progress

Ceiling joists with first-fix service pipes beneath a timber floor structure.

Structure – Ceiling joists and first-fix service runs

Floor boards being installed beside a temporary workbench and stripped masonry walls.

Structure – Floor boarding beside the temporary workbench

Boarded floor spanning the room before wall finishes and final fittings.

Structure – Boarded floor before internal finishes

Carpentry

New timber staircase installation during first-fix carpentry

Carpentry - Staircase installation

Loft landing carpentry with rooflight opening

Carpentry - Loft landing and rooflight

Timber partitions and foil-faced roof insulation in the Putney loft before boarding.

Carpentry – Loft partitions and insulated roof framing

Internal wall framing with plywood backing and visible service routes in Putney.

Carpentry – Internal wall framing and service routes

Roof insulation and timber framing around an opening in the Putney loft ceiling.

Carpentry – Roof insulation and framing around the ceiling opening

Foil-faced roof insulation held between timber battens above loft wall framing.

Carpentry – Insulated roof slope and timber battens

Loft room with exposed timber partitions and boarded floor before plasterboarding.

Carpentry – Loft room partitions before boarding

Timber framing around an open loft ceiling hatch beneath insulated roof slopes.

Carpentry – Framing around the loft ceiling opening

Insulated sloping roof above exposed timber wall framing in the loft.

Carpentry – Insulated roof slope and wall framing

Timber partition framing and a doorway opening beneath the insulated roof.

Carpentry – Timber partition and doorway framing

Timber studwork forming internal room openings during the Putney refurbishment.

Carpentry – Studwork forming the revised room layout

Timber wall framing with plywood backing and service openings before boarding.

Carpentry – Wall framing with plywood backing

Unfinished timber partitions with exposed service routes and construction materials.

Carpentry – Internal partition framing before finishes

Boarded floor panels within timber partitions before wall finishes.

Carpentry – Boarded floor within timber-framed rooms

Insulation fitted between exposed ceiling joists during first-fix works.

Carpentry – Insulation between exposed ceiling joists

Boarded landing beside unfinished timber partitions and doorway openings.

Carpentry – Boarded landing and partition openings

Boarded loft floor beside a window with exposed timber wall framing.

Carpentry – Boarded loft floor beside the window

Loft room with insulated roof framing and stacked plasterboard ready for installation.

Carpentry – Loft framing ready for plasterboard

Services

Underfloor heating pipes laid across the floor

Services - Underfloor heating

Underfloor heating manifold installed during services stage

Services - Heating manifold

Plumbing pipes routed through timber stud partitions with plywood backing.

Services – Plumbing pipework within timber partitions

White plumbing pipes distributed through an unfinished timber stud wall.

Services – Plumbing distribution through studwork

Shower tray and plumbing preparation within an unfinished timber-framed bathroom.

Services – Bathroom pipework and shower-tray preparation

Underfloor heating pipes beside unfinished timber wall framing and service routes.

Services – Floor heating and partition service routes

Underfloor heating loops across a room floor beside a large window.

Services – Underfloor heating beside the room window

Heating pipes laid on the floor beneath exposed timber ceiling and wall framing.

Services – Heating loops beneath exposed ceiling framing

Underfloor heating loops extending across the revised room layout.

Services – Underfloor heating around the new room layout

Progress & Details

Boarded loft room taking shape after first fix

Progress - Loft room taking shape

Recessed boarded loft ceiling detail

Detail - Recessed loft ceiling

 

Related services: Carpentry, kitchens and bespoke joinery

Need carpentry or refurbishment work in Putney?

 

bottom of page